Slab, rebar and ring beams
A cast-in-place slab is one continuous plate that ties the walls together and carries the upper floor. The slab and the ring beams work together, so we pour them in one go, once the formwork and rebar for both are ready.
Formwork
We set panels on steel props, at the level in the design. The props stand on compacted ground or on the slab below, so they do not sink under the concrete.
Rebar
Two tied meshes of bars, with spacers and extra bars over the supports. The bar sizes and spacing come from the structural drawing.
Ring beams
We pour them together with the slab, over all load-bearing walls. That way slab and walls are tied into one frame.
Concrete
The concrete comes from the plant and goes in in one piece, with no joints. The pump reaches over the walls, so nobody carries concrete up in buckets.
The price of a floor slab
All pricesA slab is priced per m³ of concrete poured. The price is labour, formwork and reinforcement included.
| Work | Unit | Price from |
|---|---|---|
| Reinforced concrete floor slablabour: formwork, reinforcement and pouring | m³ | 1,550 lei |
| Reinforced concrete strip foundationlabour: reinforcement and pouring | m³ | 900 lei |
| House shellfoundation, walls, floor slabs, roof, with materials | m² | 5,800 lei |
A house is priced per m² of built area, materials and labour included. Separate jobs are priced for labour: you buy the materials, or we bring them at the price on the receipt. The exact amount goes into the stage-by-stage estimate once we have seen the design, the plot and the soil.
Cast in place or precast?
A cast slab is poured in one piece, to the exact shape of the house, and ties all the walls together. Precast planks go in faster, but need a crane and fit awkwardly on irregular houses. That is why a cast slab suits houses with many corners or wide spans between walls better.
On private houses we usually cast in place. The slab is poured once the masonry of the storey is done, and before the upper floor or the roof. We leave the stair opening and the passages for the chimney and pipes in the formwork from the start, so the concrete never has to be cut afterwards.
How we cast the slab
The pour takes a day; the preparation and curing take a few weeks.
Formwork
We set the props and panels at the level in the design. We check the formwork is level, because the slab comes out exactly as the formwork is.
Reinforcement
We tie the bottom and top meshes and the ring beam bars. Before the pour we show you the rebar, so you see what stays inside the concrete.
Pouring
We pump the concrete in one go and vibrate it. We smooth the surface with a screed board, so the floor screed on top can be thin.
Curing
We leave the props under the slab until the concrete reaches the strength in the design. In hot weather we wet and cover it so it does not crack.
Frequently asked questions
How thick is a cast floor slab?
On private houses usually 15-20 cm. The exact thickness and rebar come from the design, based on the span between walls. A slab that is too thin sags over time; one that is too thick loads the walls and foundation for nothing.
When can walls go up on the slab?
We build on the slab once the concrete has gained strength. You can walk on it after a few days, and the props usually come out after three to four weeks; until then we do not stack heavy pallets of blocks on it.
Do you pour ring beams without a slab?
Yes. The ring beam under the roof is poured even when no slab goes over the top storey, to tie the walls and carry the roof frame. The wall plate, the beam the rafters rest on, is fixed to it.